The Hilton Garden Inn (“HGI”) had rock and existing concrete foundations from the previous building’s structure. With 1 Harmon Meadow Boulevard - Secaucus, NJ 07094
HGI having 2-Stories of below-grade structure as well, Rinaldi had to perform rock & concrete excavation & breaking.
Rinaldi utilized Line-Drilling to minimize vibration as a part of the firm’s vibration & crack protection and monitoring
processes. As part of the SOE given the 2-Stories of below-grade Cellar and Sub-Cellar structure, Rinaldi had to drive
Steel H- Piles or Soldier Piles and install Timber Lagging along South (Street) Elevation. 201-601-4065 - [email protected]
Property is roughly 85’ x 100’ = 8,500 SF. At the 3rd Floor through the 24th Floor the building sets-back at roughly 4,600
SF.
Complete with a 2,000 SF Kitchen, a 2,000 SF Restaurant, a 1,500 SF 1st Floor Bar/Lounge and a Spectacular 2,200 SF
Terrace Bar/Lounge service by 2-Story, Glass Elevator in addition to a Laundry Room, Meeting Rooms, a Board Room &
Administrative Offices.