SPECIALTY PROJECT MetLife Stadium
East Rutherford, NJ
The Rinaldi Group’s diversity can be clearly demonstrated by this Fast-Track project performed between VALUE
April and July 2010 at the New Meadowlands Stadium in East Rutherford, NJ. TRG not only had to $350,620 Union
provide it’s own structural & electrical engineering, but it had to do it in virtually 8-weeks with lead-time
required for steel fabrication and the Project had to be performed Union. ARCHITECT
Ewing Cole
TRG had to work two (2) 12-hour shifts per day, 7-days per week to comply with Meadowlands Complex
scheduling, specifically, this Union work had to be completed with the signs operational on or before the CM
Jon Bon Jovi Concert in June Above. MetLife specialty advertisement Cornerstone sign. 2010. TRG not Skanska Construction
only 4th Cornerstone sign not shown was for Pepsico’s Pepsi-cola. completed the work on time, but it
saved the client roughly $200-K in the process. SIGN DESIGNER
Landmark Sign Group
CLIENT
Metro-Media Technologies
New York, NY
PROGRESS
Completed 7-30-10