Page 233 - TRG AIA-305 Prequalification Statement
P. 233

Michael izzo



     The                                                                        Project SuPerintendent
     RINALDI
     G  R  O  U  P


     Flintlock construction Services – New York, NY
     Project Superintendent
     Springhill Suites – 25 West 37th Street
     20 Stories, 72,000SF, 173 room Hotel:
     • Lead superintendent responsible for the construction of new York city’s first SpringHill Suites by Marriott.
     • oversee and direct all construction activities from concrete superstructure to tco.
     • oversee and direct the installation of the projects façade system which included a combination of metal panel systems, punch windows, a slopped curtain
     wall system on the upper floors, and Storefront installations included an extended canopy
     • coordination of the interior program from framing to finish carpentry
     • coordination of mechanical trades and installation of all mechanical equipment, including the installation of city services, fire alarm systems installation
     and approval, and elevator installation and turn over.
     • responsible for the installation of all finishes in guestrooms and public spaces
     • Worked directly with Marriott representatives to ensure brand standards were followed during all phases of contraction, including mock up installation and
     approval, Brand fire life safety requirements, and punch-list and final turnover of guestrooms.
     • Assisted ownership with the installation of FF&e for guestrooms and public space
     • Held weekly on site safety and progress meeting with subcontractors and owners representatives to review project schedule, coordination issues, and
     project overview

     Flintlock construction Services – New York, NY
     Project Superintendent
     Fairfield inn & Suites – 325 West 33rd Street
     23 Stories, 96,000SF, 239 room Hotel:
     • Monitor and assist with all aspects of construction from superstructure to core & shell
     • responsible for the coordination and installation of the concrete superstructure
     • Assisted with the coordination of mechanical contractor for the rough in of guestrooms M.e.P.S systems
     • responsible for the coordination and start of the interiors program for guestroom
     construction

     cNY Builders – New York, NY
     Project Superintendent
     Double Tree hotel – 8 Stone Street
     43 Stories, 150,000SF, 399 room Hotel:
     • oversee all aspects of construction from core & shell to tco sign offs.
     • responsible for monitoring concrete superstructure. Working directly with the concrete subcontractor & structural engineer throughout the superstructure
     phase.
     • Monitor & track the installation of all façade work which included the installation of modular bricks, utility bricks, an eFS system, and punched windows.
     • Monitor all rough carpentry & drywall activates. resolving field condition issues & preparing rFi’s for submission to architect.
     • responsible for monitoring and installation of the Hotel’s storefront which was a combination of handset stone, thin stone paneling system and curtain
     wall installation.
     • Assisted with the coordination and installation of the con ed vaults from foundations to vault placement.
     • responsible for the completion of all public spaces which included a fitness center, a business center, two lobbies, a full sized kitchen & restaurant.
     • Schedule third party inspections.
     • organize & hold weekly project safety meetings & foremen meetings.
     • responsible for completing weekly progress tracking & field look a head schedules.
     • Working directly with the project management team in resoling field issues, preparing requisitions for payments, daily reporting, field scheduling, payroll
     reporting & addressing owner / architect concerns.
     • Worked directly with the project site safety manager in addressing & resolving all safety issues.