     The Rinaldi Group of florida, llC – miami, fl
     Chief Operating Officer

     flagler Station, West Palm Beach, fl
     Project executive
     ground up construction of an 8-Story, 162,000 Sf rental apartment building with 3rd floor pool deck,
     fitness center, ground floor retail and amenity spaces in downtown West palm Beach. this is a high profile
     affordable housing project for the City of West palm Beach with involvement from the Mayor’s office and
     funding provided by florida housing finance Corporation (fhfC) and the Community redevelopment agency
     (Cra) of West palm Beach. the project also includes a public Linear park utilizing historic railroad cab and
     tracks with modern hardscape and landscape. VaLUe: $22,400,000 – SiZe: 8-Stories, 162,000 Sf, 94 Units
     - arChiteCt: Corwil architects – StrUCtUraL engineer: Mcnamara Salvia - Mep engineerS: rpJ. CiViL
     engineer: Wgi.
                                                                                              [email protected]
     i5 Wynwood, miami, fl
     Project executive
     8-story, concrete structure with rooftop pool deck and amenities. the building consists of 63 co-living rental units, with a total of 217 rentable bedrooms
     around a central courtyard and is comprised of 125,000 gross square feet. the project presents numerous challenges including a building with zero lot
     lines, minimal lay-down area, limited MOt options in a high density area in Wynwood. the national co-living company, Common is the operational partner of
     this project. apartments will be shared by tenants who rent individual bedrooms within the 3 or 4 bedroom floorplans. the rinaldi group worked extensively
     with the related group and the design team during preconstruction to identify V.e. opportunities such as the elimination of the Mezzanine level, relocation
     of the generator room and reduction in the pool deck amenity space. VaLUe: $20.5MM – SiZe: 63 Units 125,000 Sf - arChiteCt: arquitectonica -
     StrUCtUraL engineer: B&J Consulting engineers - Mep engineer: JaLrW engineering group - OWner: the related group.

     Warren Henry auto Group, north miami, fl
     Project executive
     this facility is a state-of-the-art $80 million, 8 Stories, 750,000 Sf auto dealership / headquarters for the Warren henry auto group in north Miami,
     the largest auto dealership facility in South florida. this was a distressed project where trg was called in at 40% completion to replace the terminated
     gC and “right the ship” to achieve tCO and CO. We provided a full Construction Management team including project executive, general Superintendent,
     Superintendent, hVaC Superintendent and electrical Superintendent. through our expertise and direction, the project was put back on track by providing
     the required leadership as we worked with trade contractors to ramp up their crew sizes and bring in competent foremen.  We achieved tCO ahead of our
     schedule goals after being 12 months behind schedule with the former gC. there were numerous items of non-conforming work that were identified by trg
     and corrective work was undertaken after consultation with the architect, engineers and third party inspectors. VaLUe: $80,000,000 – SiZe: 8-Stories,
     750,000 Sf - arChiteCt: rVL architecture and Design.

     The Raleigh Hotel, miami Beach, fl
     Project executive
     the project consists of the restoration and conversion of the historic 9 floor hotel into a modern 5-Star luxury hotel and the construction of a new
     beach-side pavilion Building with a 11,000 Sf basement and 8 new townhouses above. Major structural repairs were required including concrete
     restoration and repairs to aging terra cotta block that provided the structure for the grand lobby ceiling. a new steel bridge was constructed to provide
     access from the north side of the property over the 11,000 Sf pit that had been excavated and waterproof for the basement of the pavilion structure. a
     $1,500,000 temporary tropical garden was constructed on the east side of the property adjacent to the beach for a promotional sculpture garden with
     over $10,000,000 of art curated throughout the garden. VaLUe: $50,000,000 – SiZe: 9-Stories, 102,000 Sf – arChiteCt: Kobi Karp architecture -
     StrUCtUraL engineer: YhCe - MepS engineerS: Ventrop engineering - CiViL engineer – Ocean engineering.