Page 234 - TRG AIA-305 Prequalification Statement
P. 234
Michael izzo
The Project SuPerintendent
RINALDI
G R O U P
assistant Project Superintendent
element hotel – 311 West 39th Street
39 Stories, 180,000 SF, 418 room Hotel:
Assistant superintendent responsible for the overseeing all aspects of construction.
• Assisted in monitoring the installation of foundations, including excavations, underpinning, & concrete placement.
• Assisted with preconstruction planning, including site logistics, permitting, & field office coordination.
• Monitor all phases of concrete superstructure, including tower crane foundation installation, tower crane installation, reinforcement installation, concrete
embed installation, concrete placement, & scheduling of third party inspections.
• Monitor Masonry façade installation, including the installation of multipoint scaffold systems, cMu & Brick installation, scheduling of third party
inspections.
• oversee the start of the interiors program, including the monitoring, scheduling & tracking of mechanical trades, drywall subcontractors, & elevator
subcontractor.
• organized and held on site meetings, including weekly project safety meetings with subcontractors, weekly foremen’s meeting, project progress &
scheduling meetings.
• Working directly with the project management team in resoling field issues, preparing requisitions for payments, daily reporting, field scheduling, payroll
reporting & addressing owner / architect concerns.
• Worked directly with the project site safety manager in addressing & resolving all safety issues.
assistant Project Superintendent
Tri-Pak hotels – 337, 339, 343 West 39th Street
hampton inn, candlewood Suites, holiday inn express
Hampton inn, 32 Stories, 75,000 SF, 186 room Hotel
candlewood Suites, 32 Stories, 79,000 SF, 188 room Hotel
Holiday inn express, 36 Stories, 72,000 SF, 210 room Hotel
Assistant superintendent responsible for the overseeing all aspects of construction of
three hotels that were built as one core & separated during finishes.
• oversee & monitor the completion of concrete superstructure.
• Monitor the installation of façade systems. each Hotel had a separate design. Façade systems including four different modular bricks, utility bricks, a metal
panel system, & an eiFS system.
• Monitor the installation of punched windows.
• oversee & monitor the interiors program including all mechanical trades, drywall, elevators, & finishing trades.
• responsible for creating & distributing construction tco punch lists for all three hotels.
• organized and held on site meetings, including weekly project safety meetings with subcontractors, weekly foremen’s meeting, project progress &
scheduling meetings.
• Working directly with the project management team in resoling field issues, preparing requisitions for payments, daily reporting, field scheduling, payroll
reporting & addressing owner / architect concerns.
• Worked directly with the project site safety manager in addressing & resolving all safety issues.
Project Superintendent
213 Pearl Street
Project Superintendent in charge of overseeing the demolition of a Historic 1830 era
warehouse. An emergency demolition order was executed by the new York city
department of buildings due to the stability of the building.
• review site logistics with Project management team. Set up safety zone with demolition contractor.
• Monitor the demolition of the building with forensic engineers & the department of buildings.
• oversee the filling & Grading of the site.
• oversee the waterproofing of exposed adjoining properties.